Project Description
Location: Iraq / Turkish Border
Project Status: Completed
Client: State Organization for Oil Projects – SCOP
Project Design: TEC-ENET
Turn-key Contractor: Consortium of Enka and TOYO Engineering
Construction Period: March 1983 – October 1984
Project Description
Replacement of pumps and motors at the existing stations IT1, IT2. Modification of dispatching center. Extension of the meeting station near the Iraqi- Turkish border and addition of the 4th meter run. Construction of two new pump stations IT 1A and IT 2A complete with high voltage substation, MV substation, fire fighting/fire alarm system, Tie-in of new stations to existing pipeline by a double position stopple operation. Replacement of computer system at IT1, dispatching center and extension and modification of remote control, central control and telecommunication systems. Construction of residential area at IT 1A station.
Eren’s Scope of Work: Project Management