Project Description
Location: Azerbaijan / Baku
Project Status: Completed
Construction Period: October 2002 – May 2003
Main Contractor: EREN Construction
Client: State Concern of Civil Aviation “Azerbaijan Airlines”; AZAL
Project Description
Baku Domestic Airport Terminal Project which is awarded by AZAL, The State Concern of Civil Aviation “Azerbaijan Airlines”, consists of the construction of the Terminal Building having an area of 10,500 m2. Demolition works, çivil construction works, architectural works, mechanical and electrical works are the main scope of works of project. Besides the construction of several offices, restaurant, cafes, ticket sale offices, the construction of the Presidential VIP section is other scope of the construction of the Terminal. In addition to the Terminal, construction of Heating Center and Transformator Building are other scopes included in the Project.